Saturday, October 25, 2008

Back to Making Messes

It has been almost a week since I have been able to post anything because I have been busy, but recent developments have been; We made a trip to Tillamook with our pick up because Ray was going to loan use his scaffolding, on the way back the pick up quit running, twice, bad points was the culprit, but both times GOD made sure there was just enough light so that I could file them a little and then reset them and get a little further down the road.
Also this week the Electrician showed up and started wiring for our lights and ceiling fans. Using Ray's scaffolding they were able to get the fan and one fixture in my shop,
They then discovered they had the wrong bulb for that fixture, so then they concentrated on Stephanie's area and the bathroom.
they worked 1 1/2 days then took off. Meanwhile Steve showed up and the two of us started putting up the rest of the sheet rock,
when the last piece we put up almost took me off the stairs while Steve was repositioning, we decided that was enough for the day.
Also Mel from the Alarm Company showed up and we decided on what we needed for this building and he should be back on Tuesday to Install it.