Sunday, November 02, 2008

Winding Down

With the rain coming the gutter guys came back to put the downspout on the front gutter, but one of the crew had thrown some of the pieces away so they had to use white ones temporarily. 
In the mean time the electricians had finished putting the lights and ceiling fan in Stephanie's area.
Steve and I have kept busy putting sheetrock on the rest of the walls,


Friday the inspectors for the county showed up first the plumbing inspector and that passed without a problem, then the electrical inspector showed up and there were a couple of small issues that Ben has already taken care of.
I have installed the door for the closet (Water heater room), and Ben gave us a light for the bathroom that we will put up in a grid type ceiling.
But for now I am taking a day off, just going to VEG and watch football.