Sunday, August 03, 2008

Hurry-up and Wait


Well the professionals were here and it didn't take them long to level the site.

Now we just are waiting for Parker Building to come and set the posts, they say that they will start on Aug 18th, give or take. 
Setting the poles will take some time because they will have to drill the holes and then put concrete in the bottoms and then get an inspection before they can set the poles and finish pouring the concrete, but once the poles are in place it should not take them long to put the building together.
While they were here I asked them to remove the stump that was on the north side of the house, and move all material they removed to the south edge of the property to cover the drain culvert.